Since the outset, I have been questioning the length of the One Barnet contract. In particular, I have repeatedly asked why we needed a ten year contract. The response from the Council has been the length of contract is necessary to recover the investment made by the contractor. Indeed, I think this was the point made by that knowledge Councillor Rowan Quigley-Turner at the Business Management Overview and Scrutiny Committee meeting last October
We have now found out that in fact Barnet Council have funded £16 million of investment. This is a fundamental change to the terms that were originally set out when the council made the decision to appoint Capita. Certainly there was absolutely no mention of the Council funding the investment when the decision was taken by Cabinet in December 2012.
I remain concerned that making such a fundamental change to the contract, post award, breaches EU tendering rules - unless it was previously agreed and cabinet were aware but the deal was kept secret. However, setting that aside, the response from the Council should have been to seek a reduction in the length of the contract. Limited investment = shorter contract term; that is standard business practice. This could have been Barnet's opportunity to cut the contract to, say, five years with a break clause at three years but this didn't happen. This is a serious and naive error demonstrating to me that there is a lack of financial rigour by those administering this contract.
As a final point, Barnet have now invested in excess of £26 million in this contract, including over £10 million on professional advisors. Just think what an in-house team could have delivered with just half that level of investment. But as we all know One Barnet has been one of the most successful con jobs in local government history.
Showing posts with label One Barnet Outsourcing. Show all posts
Showing posts with label One Barnet Outsourcing. Show all posts
Saturday, 5 October 2013
Tuesday, 25 June 2013
Barnet Cabinet - Just Not Listening
Although the evening was generally a disappointment the one highlight was when Mrs Angry got rather cross with naughty councillor Robert Rams and told him off for sniggering and tweeting while she was talking. Well done Mrs Angry!
I would love to have included a link to all the questions and answers but the Council has not yet published them. However, in a self indulgent moment I have included the speech I gave below.
As I have stated many times, I have no ideological issue
with outsourcing per se, so I come at this contract from a perspective of: will
it work, will it deliver the promised results and do the risks outweigh the
rewards? And risk is my biggest worry with this contract.
Risk number one - are you going to be able to manage this
contractual relationship once the contract is signed? I am gravely concerned
that over the last two years you have been deskilling the council with interims
and/or Agilisys fulfilling so many key roles. When this and the NSCSO contract
start there is going to be a massive skills vacuum on the council’s side and
that will place you in an incredibly weak position in the JV. You only have to
read through the council’s accounts to see how many senior posts are filled by
interims. I have been going through Agilisys invoices as part of the inspection
of accounts and their reach within the council is shocking. You have created a
consultancy dependent culture in the council and you are going to pay for that
dearly when this contract kicks into gear.
Risk number two – will entering into a joint venture force
you, directly or indirectly, into making unpalatable decision. The shareholders’
agreement will set out rights and obligations on both parties. We have heard a
great deal about Capita’s obligations but I have not as yet heard a single
council obligation. Do you think there aren’t any? If there aren’t then I doubt
very much it is a JV because by the very nature of the agreement both parties
have responsibilities and obligations. Whilst you as a shareholder may insist
on certain actions being taken or not taken, your directors on the JV board
through which you decisions can be enacted have a fiduciary responsibility to
the JV and that is where the problems will arise. I have a horrible feeling
that when certain services are deemed unviable or when income streams don’t
materialise your directors who sit on the board of the JV will be obligated to
make some pretty difficult decisions which you as councillors may disagree with
but you will be powerless as they are your representatives.
Risk number three -
will there be a cultural fit? There will be a massive cultural difference between
Barnet and Capita. You are a not for profit organisation focused on delivering
services and for want of a better phrase doing the right thing. Capita is a
FTSE 100 company focused on shareholder return. That cultural mismatch can work
satisfactorily in a straight contract but when you form a JV it becomes much
more difficult because you have to adapt to your partner’s culture and that I
fear will be a massive shock for Barnet. No mention of cultural fit has been
made at any stage of this contract and that suggests it has been either
overlooked or ignored.
There are many more risks that I could mention but sadly
there is no time. However, the one thing that you could at least do to test
these risks is undertake independent due diligence. I simply cannot understand
why you have refused to bring in an independent expert to carry out financial
and commercial due diligence. You have had only one set of opinions, those of
your expensive advisors. All the way through they have been advising you to
continue with this process – well they would wouldn’t they because this project
is generating millions of pounds in fees for them.
Any sensible, rational person would have said, “before I
make this massive decision I need a second opinion, I need to double check the
thinking and what is on offer”. If you had had a second opinion on the Catalyst
contract perhaps you wouldn’t have been landed with a £10 million bill. If you
had had a second opinion on the Your Choice Contract perhaps it wouldn’t be in
financial crisis.
Three weeks and £40,000 would give you at least some comfort that you were doing the right thing. But you have resolutely refused to take a second opinion. Well that, in my opinion is probably the biggest risk of all; it is arrogant and it is reckless. You still have time – think again - get an independent second opinion.
Labels:
Barnet Council,
DRS,
not listening,
One Barnet Outsourcing
Sunday, 9 June 2013
My Questions on the DRS Contract
On Tuesday there is a meeting of the Budget & Performance Overview & Scrutiny Committee (7pm Hendon Town Hall). Set out below are the questions I have submitted:
1. How
much additional gross revenue is required to generate the net
income growth share to Barnet of £33.8 million?
2. What
circumstances have changed between March 2011 and today to justify a tripling
in net income growth?
3. In
the March 2011 business case it stated that cost reductions over the period of
the contract would amount to £19.7 million yet the Capita bid suggests the
savings are now forecast at only £5.3 million or just over £500,000 per annum.
What reason has been given for a saving that is only 26.9% of that originally
forecast.
4. At
Table 7.1 in the business case it illustrates that the DRS staff numbers will
stay relatively static over the period of the contract. How can the same number
of staff generate so much more additional revenue?
5. At
Table 8.2 in the business case it suggests that the £5.3m guaranteed benefit
represents a saving of 3.5% of costs. It also says that CSL will retain 13% of
the cost savings as their fee. Based on my calculation that means that CSL will
receive £31.8 million of the costs reduction. Does this seem to be an equitable
split of cost savings?
6. Where
will the 21% reduction of core operating costs be made given that staff numbers
are virtually unchanged over the period of the contract.
7. At
Table 8.2 in the business cases it states that pre-purchasing of graves will
deliver additional benefit. As an advance payment for a service to be provided
in the future surely it should not be counted as additional revenue?
8. At
Table 8.2 in the business cases it states that there will be extended opening
hours (at Hendon Cemetery and Crematorium) and additional cremation activities.
What opening hours are envisaged and will this mean that local residents will
have to wait longer for their loved ones to be cremated unless they choose an
early morning or late night slot?
9. How
much additional highways advertising will we be forced to endure in order to
generate the additional £9.8 million of guaranteed benefit?
10. Of
the £6 million investment in IT what is the phasing of that investment over the
10 year contract period, what specific software will be purchased and what
mechanism is in place to ensure that the money promised is actually spent?
11. Where
specifically will the DRS staff be located?
12. How
many posts will be joint employment contracts?
13.
What happens if council and Members’ do not
approve new services or changes to fee levels or fee structures and how does
this impact on the guarantees?
14.
If the contract is terminated early how much
will Barnet have to pay CSL in compensation?
15. When
a planning decision is made, who will make that decision, a Barnet council
employee, a Capita employee or an employee of a new joint venture company?
16. Given
that the report states that Capita Symonds will maximise the financial and
economic benefits of new developments including increase receipts of New Homes
Bonus what reassurance can we have that they will not push through massive new
housing developments simple because they have a financial incentive to do so?
17. Who
will sit on the board of the Council wholly owned company that will manage its
interests in the Joint venture company, how many company directors will be
created and how much will they be paid?
18. Will
directors of the Council wholly owned company sit on the board of the joint
venture company and what level of decision making will they have discretion
over?
19. What
provisions are in place to stop the directors of the council wholly owned
company or the joint venture from paying themselves excessive salaries?
20. What
is the anticipated level of corporation tax payable by the joint venture
company over the ten year period of the contract.
21. On
page 12 of the business case it states that one of the reasons why a joint
venture was favoured over the original strategic partnership is that “the risks
were lower”. Please can you clarify which risks are lower under the JV model
and are there any risks that are higher?
22.
At page 14 in the business case it states that
the council reserves the right to veto salary and rewards schemes above
£150,000. Is that £150,000 in total for all DRS staff or £150,000 to any one
individual?
23.
At the end of the 10 year contract how will the
joint venture be dissolved, what liabilities will accrue to the Barnet wholly
owned company and how will DRS staff be separated from the staff carrying out
duties for other customers?
24.
Why are 30 posts to be added in year one only
for them to be removed in year two, will the posts to be removed in year
two be the individuals are were brought in in year one and what
safeguards do existing staff have that Capita will not simple bring in 30 new
staff on much lower terms and conditions and then make 30 Council TUPE’d staff
redundant at the end of year two.
25.
At the end of the contract can the shares in the
JV owned by the Barnet wholly owned company be sold to a third party?
26. Why
was this report cleared by Trowers & Hamlins not the council’s own legal
service (outsourced to Harrow Council) and does this not represent a massive
conflict of interest given that Trowers & Hamlins have provided legal
advice on the outsourcing project?
27. Why
were registration services included in the 2011 business case but excluded from
the Capita bid and who will provide registration services when the DRS contract
is let?
28. Please
can you tell me what, specifically, is the Barnet Observatory?
29. Is
there any requirement in the contract for Capita Symonds to hold open meetings
with the general public to explain what they are proposing and how the new
contract will operate?
30. Will
the chairman consider setting up a separate workshop meeting open to and
involving members of the public at which a more detailed analysis of the
contract proposals can be discussed.
Let's see if I get some clear answers!
Friday, 7 June 2013
Barnet DRS - When is a Guarantee not a Guarantee?
The Barnet DRS contract will be considered at the Budget & Performance Overview & Scrutiny committee on Tuesday 11 June. You can see the papers here. This week I have been flagging up major areas of concern that I hope someone from the Council can address. Today I want to look in more detail at the so called "Guaranteed Benefits".
In the DRS Business Case much has been made about the guarantees that will be provided to Barnet around the £39.1 million financial benefits. However, this guarantee appears to be between the Joint Venture and Barnet Council which is fine until you realise that Barnet Council will be a major shareholder in the Joint Venture. The council shares will be held by a wholly owned council company one step away from the council but still 100% owned by the council. In the DRS business case (page 38) where it identifies all of the financial benefits it states:
"The description of benefits sets out the expected activities that will achieve the total benefits. However, should any of these activities prove to be unviable, the joint venture is obliged to develop alternative proposals to meet the guaranteed financial benefit rather than it being reduced."
My reading of this very subtle caveat is as follows: Capita put in an ambitious budget which gets everyone excited. They then lock in Barnet to the Joint Venture through the council owned standalone company. When it transpires that they can't make the budget for some reason (such as when residents kick up a massive stink when cremation charges sky rocket to generate the additional £4.3 million net profit), Capita say to their joint venture partner (who is the council) "Right partner, you have to agree to other ways to make up this £4.3 million so we are going to have to push through a lot more commercial development in the borough or double planning charges. Take your pick". It will be the Barnet directors of their wholly owned company sitting on the Joint Venture Board who will have to make that decision. Failure to do so could possibly lead to the situation faced by Somerset Council where they ended up being sued by the joint venture, Southwest One, of which they were a shareholder.
When the decision to have a joint venture was first tabled, I expressed my concern that the council didn't fully understand what they were getting into. They talked about sharing the upside but no one talked about the risk they would be assuming. The Council will, I am sure, argue that the money to Barnet is guaranteed. Yes, but their representatives on the Joint Venture will have to collude in any decisions which may be against the wishes and best interests of the community to deliver that guarantee.
I would advise anyone who isn't familiar with Southwest One to read this most informative article.
I just hope the councillors who will be scrutinising this decision can provide some clear answers to these concerns on Tuesday but sadly I suspect they will vote on party lines meaning that this gets nodded through to be rubber stamped by the Cabinet on 24 June.
In the DRS Business Case much has been made about the guarantees that will be provided to Barnet around the £39.1 million financial benefits. However, this guarantee appears to be between the Joint Venture and Barnet Council which is fine until you realise that Barnet Council will be a major shareholder in the Joint Venture. The council shares will be held by a wholly owned council company one step away from the council but still 100% owned by the council. In the DRS business case (page 38) where it identifies all of the financial benefits it states:
"The description of benefits sets out the expected activities that will achieve the total benefits. However, should any of these activities prove to be unviable, the joint venture is obliged to develop alternative proposals to meet the guaranteed financial benefit rather than it being reduced."
My reading of this very subtle caveat is as follows: Capita put in an ambitious budget which gets everyone excited. They then lock in Barnet to the Joint Venture through the council owned standalone company. When it transpires that they can't make the budget for some reason (such as when residents kick up a massive stink when cremation charges sky rocket to generate the additional £4.3 million net profit), Capita say to their joint venture partner (who is the council) "Right partner, you have to agree to other ways to make up this £4.3 million so we are going to have to push through a lot more commercial development in the borough or double planning charges. Take your pick". It will be the Barnet directors of their wholly owned company sitting on the Joint Venture Board who will have to make that decision. Failure to do so could possibly lead to the situation faced by Somerset Council where they ended up being sued by the joint venture, Southwest One, of which they were a shareholder.
When the decision to have a joint venture was first tabled, I expressed my concern that the council didn't fully understand what they were getting into. They talked about sharing the upside but no one talked about the risk they would be assuming. The Council will, I am sure, argue that the money to Barnet is guaranteed. Yes, but their representatives on the Joint Venture will have to collude in any decisions which may be against the wishes and best interests of the community to deliver that guarantee.
I would advise anyone who isn't familiar with Southwest One to read this most informative article.
I just hope the councillors who will be scrutinising this decision can provide some clear answers to these concerns on Tuesday but sadly I suspect they will vote on party lines meaning that this gets nodded through to be rubber stamped by the Cabinet on 24 June.
Thursday, 6 June 2013
Barnet DRS - Increased Charges at Hendon Cemetery and Crematorium
Going through the DRS Business Case which will be discussed at the Budget & Performance Overview & Scrutiny Committee on 11 June, there are some very worrying statements which every resident should be concerned about.
Hendon Cemetery and Crematorium has been identified as generating an extra £4.3 million of net additional revenue. That is just £1 million less than Barnet will receive from all of the costs savings over the period of the contract. They will generate this revenue through "Pre-purchased graves, extended opening hours, additional cremation activities". Now we don't have the full details of exactly how this will be generated but to my mind it does not stack up.
Pre selling graves seems a bit tasteless to me but more to the point it is just bringing forward income that will be realised at a later date so after the end of the contract we run the risk of having lots of burials to fulfil without the income.
More worryingly is the extended opening hours and addition cremation activities. Are they proposing hosting budget late night cremations with higher prices for peak periods. This runs the risk of pricing out the less well off to late night and early mornings. I wonder if this is what was envisaged when the title EasyCouncil was previously used?
As for the additional cremation activities, does this mean pet cremations? Who knows because there is absolutely no details and as ever the contract itself is strictly confidential. Hopefully Tuesday will give us a few answers.
Hendon Cemetery and Crematorium has been identified as generating an extra £4.3 million of net additional revenue. That is just £1 million less than Barnet will receive from all of the costs savings over the period of the contract. They will generate this revenue through "Pre-purchased graves, extended opening hours, additional cremation activities". Now we don't have the full details of exactly how this will be generated but to my mind it does not stack up.
Pre selling graves seems a bit tasteless to me but more to the point it is just bringing forward income that will be realised at a later date so after the end of the contract we run the risk of having lots of burials to fulfil without the income.
More worryingly is the extended opening hours and addition cremation activities. Are they proposing hosting budget late night cremations with higher prices for peak periods. This runs the risk of pricing out the less well off to late night and early mornings. I wonder if this is what was envisaged when the title EasyCouncil was previously used?
As for the additional cremation activities, does this mean pet cremations? Who knows because there is absolutely no details and as ever the contract itself is strictly confidential. Hopefully Tuesday will give us a few answers.
Saturday, 1 June 2013
Barnet Outsourcing and a Capita inspired £167k solution
In the latest Delegated Powers Report it notes the huge problems of staff retention in customer services, revenues and benefits and procurement departments that are due to be outsourced. The report states:
"The current staff turnover rate within these services shows a loss of circa 32% of total staff numbers throughout the life of the procurement and early stages of mobilisation. This directly affects these public facing front line services and will be reputationally damaging for the Council".
Now this report tries to pin the problems currently being experienced on the judicial review and appeal but the statement above reveals the truth that the outsourcing programme itself, where staff know they will lose their jobs, has caused them to leave in their droves - why wouldn't they.
So to get around the problem CAPITA have suggested a solution which is to use CAPITA'S "overflow staff" (I guess they mean their call centre staff in Darwen and Blackburn) to help the staff that remain and who await their redundancy notices if the judicial review appeal is unsuccessful.
The interim contract will cost £167,625 and will only run until 21 June in the hope that the judicial review appeal will have been heard by then (as they say, Barnet have two hopes, Bob Hope and No Hope and Bob Hope is dead). Part of this deal also includes what they term a" skeleton team" to prepare for the handover after the appeal hearing.
The report states that "This interim measure is for a 4 week period and does not prejudge the outcome of the Judicial Review appeal proceedings nor is the Council entering into the NSCSO contract prior to its formal commencement". I think that is to keep the lawyers happy.
Now we wouldn't be in the mess of the Council had actually carried out a proper consultation exercise in the first place, something Lord Justice Underhill was clear about in his judgement and I suspect one of the key reasons that an appeal on the technicality of timing has been allowed.
All of these types of problems should have been anticipated and should have been built into the risk register when the entire outsourcing programme was being considered. As ever our Councillors stuck their head in the sand and believed everything they were told by their hugely expensive advisors.
This is a mess and has been from the start. The DRS contract looks even worse given that it seems almost entirely dependent on generating new business from other local authorities something which brought about the demise of the infamous Southwest one Contract and which closer to home has been shown not to work for the beleaguered Your Choice Barnet contract. Councillors need to face up to reality that the whole One Barnet outsourcing project has been an extremely expensive mess and the sooner they recognised it and seek an alternative solution the sooner they can refocus on running an efficient and effective council.
"The current staff turnover rate within these services shows a loss of circa 32% of total staff numbers throughout the life of the procurement and early stages of mobilisation. This directly affects these public facing front line services and will be reputationally damaging for the Council".
Now this report tries to pin the problems currently being experienced on the judicial review and appeal but the statement above reveals the truth that the outsourcing programme itself, where staff know they will lose their jobs, has caused them to leave in their droves - why wouldn't they.
So to get around the problem CAPITA have suggested a solution which is to use CAPITA'S "overflow staff" (I guess they mean their call centre staff in Darwen and Blackburn) to help the staff that remain and who await their redundancy notices if the judicial review appeal is unsuccessful.
The interim contract will cost £167,625 and will only run until 21 June in the hope that the judicial review appeal will have been heard by then (as they say, Barnet have two hopes, Bob Hope and No Hope and Bob Hope is dead). Part of this deal also includes what they term a" skeleton team" to prepare for the handover after the appeal hearing.
The report states that "This interim measure is for a 4 week period and does not prejudge the outcome of the Judicial Review appeal proceedings nor is the Council entering into the NSCSO contract prior to its formal commencement". I think that is to keep the lawyers happy.
Now we wouldn't be in the mess of the Council had actually carried out a proper consultation exercise in the first place, something Lord Justice Underhill was clear about in his judgement and I suspect one of the key reasons that an appeal on the technicality of timing has been allowed.
All of these types of problems should have been anticipated and should have been built into the risk register when the entire outsourcing programme was being considered. As ever our Councillors stuck their head in the sand and believed everything they were told by their hugely expensive advisors.
This is a mess and has been from the start. The DRS contract looks even worse given that it seems almost entirely dependent on generating new business from other local authorities something which brought about the demise of the infamous Southwest one Contract and which closer to home has been shown not to work for the beleaguered Your Choice Barnet contract. Councillors need to face up to reality that the whole One Barnet outsourcing project has been an extremely expensive mess and the sooner they recognised it and seek an alternative solution the sooner they can refocus on running an efficient and effective council.
Monday, 20 May 2013
One Barnet DRS Contract - Another Disastrous Decision
Today, Barnet Council have announced they have selected Capita as the winner of the Development and Regulatory Services (DRS) contract. This is the second large contract to be awarded to Capita and now gives them control over most of what the Council actually delivers. Just for those of you who are still unaware of what this contract includes it is the following (as set out in the original tender notice):
"Services furnished by business, professional and specialist organisations. Land management services.Architectural, engineering and planning services. Technical planning services. Urban planning and landscape architectural services. Architectural services for buildings. Miscellaneous building structures. Housing services. Development of residential real estate. Feasibility study, advisory service, analysis. Project and design preparation, estimation of costs. Draft plans (systems and integration). Calculation of costs, monitoring of costs. Approval plans, working drawings and specifications. Determining and listing of quantities in construction. Supervision of building work. Supervision of project and documentation. Architectural, engineering and surveying services. Architectural and building-surveying services. Construction management services. Funeral and related services. Funeral services. Cemetery services and cremation services. Cemetery services.Cemetery maintenance services. Cremation services. Work environment services. Civic-amenity services. Car park management services. Civic betterment and community facility support services. Facility related sanitation services. Disinfecting and exterminating services. Pest-control services. Rat-disinfestation services. Fumigation services. Services related to noise pollution. Noise control services. Noise pollution protection services. Noise pollution monitoring services. Noise pollution advisory services. Environmental institution building or planning.Environmental issues consultancy services. Environmental planning. Urban environmental development planning. Environmental services. Environmental management. Environmental impact assessment other than for construction. Risk or hazard assessment other than for construction. Environmental standards other than for construction. Environmental indicators analysis other than for construction. Environmental Impact Assessment EIA services other than for construction. Environmental monitoring other than for construction. Highways engineering services. Highways consultancy services. Administrative housing services. General public services.Administration services. Engineering design services for the construction of civil engineering works. Quantity surveying services for civil engineering works. Health and safety services. Health and safety consultancy services. Advisory and consultative engineering services. Building services. Building-fabric consultancy services. Building consultancy services. Building services consultancy services. Building surveying services.Building-inspection services. Infrastructure works consultancy services. Structural engineering consultancy services. Environmental engineering consultancy services. Noise-control consultancy services. Environmental impact assessment for construction. Risk or hazard assessment for construction. Environmental standards for construction. Environmental indicators analysis for construction. Environmental impact assessment (EIA) services for construction. Environmental monitoring for construction. Commissioning of public lighting installations. Structures and parts of structures. Structures and parts. Miscellaneous structures. Parts of structures. Road traffic-control equipment. Traffic control services. Traffic monitoring services. Records management. Road transport services. Public road transport services. Support services for land transport. The London Borough of Barnet is looking for a Strategic Partner (SP), single bidder or consortium, to transform the delivery of its Development and Regulatory Services. The London Borough of Barnet wishes to work with the SP to provide a joined-up environmental regulation, design and management function that will develop and maintain the quality of the built environment and help to ensure the health and well being of our citizens. The services in scope are as follows: Strategic Services:
— Regeneration,
— Strategic planning and housing strategy,
— Highways transport and regeneration,
— Highways strategy operational services:
—— Building control and structures,
—— Planning development management,
—— Land charges,
— Highways network management,
— Highways traffic and development public health, consumer and regulatory services,
— Environmental health,
— Trading standards & licensing,
— Cemetery & crematorium".
(The registration and nationality services were originally included but have subsequently been excluded from the contract)
The services will be run as a joint venture - but we forbidden from knowing what that means or how it is structured and the contract will run for 10 years. We have been told it will save £3.9 million a year and that staffing will be kept at "broadly the current level" whatever that means. However everything associated with this contract is shrouded in secrecy because it is "commercially sensitive".
The residents of Barnet were never consulted on this matter (Justice Underhill says so) and we are unlikely to ever know the details. Ten people have now awarded two contracts worth around £500 million with the potential for significantly more and we, as residents, have no say.
And were these services terrible when the outsourcing was first envisaged. No, actually they were highly rated and efficient but that is no what this process is all about. It is about political dogma. George Osborne will be able to claim a whole load more private sector jobs have been created because every job outsourced to the private sector is claimed as a new private sector job forgetting that it is a job lost in the public sector. Now you will know next time the Conservatives claim they have created a million new private sector jobs exactly where they came from.
What gets to me most of all is the calibre of the politicians making these decisions, or as Brian Coleman put it "Young boys who are keen but don’t have the time because they are busy building their careers or relationships, or sad old pensioners who just won’t go away". All the analysis has been left to faceless consultants whose names we are not allowed to know, who have no connection with the borough and who won't be around when it all goes wrong.
This is not democracy and it is wrong.
"Services furnished by business, professional and specialist organisations. Land management services.Architectural, engineering and planning services. Technical planning services. Urban planning and landscape architectural services. Architectural services for buildings. Miscellaneous building structures. Housing services. Development of residential real estate. Feasibility study, advisory service, analysis. Project and design preparation, estimation of costs. Draft plans (systems and integration). Calculation of costs, monitoring of costs. Approval plans, working drawings and specifications. Determining and listing of quantities in construction. Supervision of building work. Supervision of project and documentation. Architectural, engineering and surveying services. Architectural and building-surveying services. Construction management services. Funeral and related services. Funeral services. Cemetery services and cremation services. Cemetery services.Cemetery maintenance services. Cremation services. Work environment services. Civic-amenity services. Car park management services. Civic betterment and community facility support services. Facility related sanitation services. Disinfecting and exterminating services. Pest-control services. Rat-disinfestation services. Fumigation services. Services related to noise pollution. Noise control services. Noise pollution protection services. Noise pollution monitoring services. Noise pollution advisory services. Environmental institution building or planning.Environmental issues consultancy services. Environmental planning. Urban environmental development planning. Environmental services. Environmental management. Environmental impact assessment other than for construction. Risk or hazard assessment other than for construction. Environmental standards other than for construction. Environmental indicators analysis other than for construction. Environmental Impact Assessment EIA services other than for construction. Environmental monitoring other than for construction. Highways engineering services. Highways consultancy services. Administrative housing services. General public services.Administration services. Engineering design services for the construction of civil engineering works. Quantity surveying services for civil engineering works. Health and safety services. Health and safety consultancy services. Advisory and consultative engineering services. Building services. Building-fabric consultancy services. Building consultancy services. Building services consultancy services. Building surveying services.Building-inspection services. Infrastructure works consultancy services. Structural engineering consultancy services. Environmental engineering consultancy services. Noise-control consultancy services. Environmental impact assessment for construction. Risk or hazard assessment for construction. Environmental standards for construction. Environmental indicators analysis for construction. Environmental impact assessment (EIA) services for construction. Environmental monitoring for construction. Commissioning of public lighting installations. Structures and parts of structures. Structures and parts. Miscellaneous structures. Parts of structures. Road traffic-control equipment. Traffic control services. Traffic monitoring services. Records management. Road transport services. Public road transport services. Support services for land transport. The London Borough of Barnet is looking for a Strategic Partner (SP), single bidder or consortium, to transform the delivery of its Development and Regulatory Services. The London Borough of Barnet wishes to work with the SP to provide a joined-up environmental regulation, design and management function that will develop and maintain the quality of the built environment and help to ensure the health and well being of our citizens. The services in scope are as follows: Strategic Services:
— Regeneration,
— Strategic planning and housing strategy,
— Highways transport and regeneration,
— Highways strategy operational services:
—— Building control and structures,
—— Planning development management,
—— Land charges,
— Highways network management,
— Highways traffic and development public health, consumer and regulatory services,
— Environmental health,
— Trading standards & licensing,
— Cemetery & crematorium".
(The registration and nationality services were originally included but have subsequently been excluded from the contract)
The services will be run as a joint venture - but we forbidden from knowing what that means or how it is structured and the contract will run for 10 years. We have been told it will save £3.9 million a year and that staffing will be kept at "broadly the current level" whatever that means. However everything associated with this contract is shrouded in secrecy because it is "commercially sensitive".
The residents of Barnet were never consulted on this matter (Justice Underhill says so) and we are unlikely to ever know the details. Ten people have now awarded two contracts worth around £500 million with the potential for significantly more and we, as residents, have no say.
And were these services terrible when the outsourcing was first envisaged. No, actually they were highly rated and efficient but that is no what this process is all about. It is about political dogma. George Osborne will be able to claim a whole load more private sector jobs have been created because every job outsourced to the private sector is claimed as a new private sector job forgetting that it is a job lost in the public sector. Now you will know next time the Conservatives claim they have created a million new private sector jobs exactly where they came from.
What gets to me most of all is the calibre of the politicians making these decisions, or as Brian Coleman put it "Young boys who are keen but don’t have the time because they are busy building their careers or relationships, or sad old pensioners who just won’t go away". All the analysis has been left to faceless consultants whose names we are not allowed to know, who have no connection with the borough and who won't be around when it all goes wrong.
This is not democracy and it is wrong.
Wednesday, 1 May 2013
Judicial Review - Maria Nash is granted legal aid for her appeal
Great news today is that Maria Nash has been granted legal aid to fund her appeal of the Judicial Review. If this were a frivolous case it would never have got out of the starting blocks but clearly legal aid have seen the merits of this case and the judgement as a good enough reason not only to fund the case itself but now to fund the appeal.
On Monday Richard Cornelius asked Maria Nash not to appeal the decision. Maybe that's because there is a good chance the ruling will be overturned. Time will tell.
On Monday Richard Cornelius asked Maria Nash not to appeal the decision. Maybe that's because there is a good chance the ruling will be overturned. Time will tell.
Tuesday, 30 April 2013
Barnet Judicial Review - is this justice?
Yesterday, the judgement on the Maria Nash's judicial review was published. I would urge as many people as possible to read this judgement because it illustrates just how unfair the justice system can be at times.
The judge, Lord Justice Underhill is critical of Barnet and is quite clear that they failed to consult with residents. However, the law believes that ordinary residents without a law degree, need to do things like study the Official Journal of the European Union (OJEU) with great rigour, to read between the lines on council papers, even when they are not explicit and to seek legal redress at the earliest possible opportunity even though they don't know what they are objecting to.
Barnet failed miserably to consult - and in the judges words;
"Although I have, out of deference to the attention given to it in the evidence, and to some extent also at the hearing, summarised the nature of the consultation about the 2010/11 and 2011/12 budgets, there is no real dispute that it did not constitute consultation about outsourcing as such. “Alternative service provision” was mentioned in the materials supplied, at least for the latter year; but no relevant information was supplied, and the exercises were plainly not designed to elicit views about it". He went on to say:
"It is clear that in the present case the Council did not make any attempt to consult on the specific question of whether the functions and services covered by the NSCSO and DRS contracts should be outsourced", and in summary he said:
"It follows that if the application for judicial review had been made in time I would have held that the Council had not complied with its obligations under section 3 (2) of the 1999 Act in respect of the decisions taken in 2010/11 to outsource the performance of its functions and services, covered by the proposed NSCSO and DRS contracts".
BUT... the case is out of time so tough luck!
I believe it was Lord Hailsham who coined the phrase "elective dictatorship" and that is exactly what we have in Barnet, a weak group that fails to represent the broad views of the residents but is able to drive through whatever policies it wants aided by the weaknesses of the democratic system we have in place. If this judgement stands it will send a green light to Barnet to be even more secretive about what they are doing, to completely ignore meaningful consultions, to ignore the broad range of views of the 356,000 residents and to go ahead with whatever it wants, because it can.
I understand that Maria Nash is going to appeal and I hope for everyone's sake she is successful.
The judge, Lord Justice Underhill is critical of Barnet and is quite clear that they failed to consult with residents. However, the law believes that ordinary residents without a law degree, need to do things like study the Official Journal of the European Union (OJEU) with great rigour, to read between the lines on council papers, even when they are not explicit and to seek legal redress at the earliest possible opportunity even though they don't know what they are objecting to.
Barnet failed miserably to consult - and in the judges words;
"Although I have, out of deference to the attention given to it in the evidence, and to some extent also at the hearing, summarised the nature of the consultation about the 2010/11 and 2011/12 budgets, there is no real dispute that it did not constitute consultation about outsourcing as such. “Alternative service provision” was mentioned in the materials supplied, at least for the latter year; but no relevant information was supplied, and the exercises were plainly not designed to elicit views about it". He went on to say:
"It is clear that in the present case the Council did not make any attempt to consult on the specific question of whether the functions and services covered by the NSCSO and DRS contracts should be outsourced", and in summary he said:
"It follows that if the application for judicial review had been made in time I would have held that the Council had not complied with its obligations under section 3 (2) of the 1999 Act in respect of the decisions taken in 2010/11 to outsource the performance of its functions and services, covered by the proposed NSCSO and DRS contracts".
BUT... the case is out of time so tough luck!
I believe it was Lord Hailsham who coined the phrase "elective dictatorship" and that is exactly what we have in Barnet, a weak group that fails to represent the broad views of the residents but is able to drive through whatever policies it wants aided by the weaknesses of the democratic system we have in place. If this judgement stands it will send a green light to Barnet to be even more secretive about what they are doing, to completely ignore meaningful consultions, to ignore the broad range of views of the 356,000 residents and to go ahead with whatever it wants, because it can.
I understand that Maria Nash is going to appeal and I hope for everyone's sake she is successful.
Friday, 26 April 2013
The One Barnet Consultant's bill hits £6.3 million
In February our dear friends Agilisys, who are helping Barnet Council implement One Barnet billed a rather modest £55,244.55. At the time I wondered if we had seen the end of their huge six figure bills. Today Barnet have published (early) the supplier payments for March and surprise, surprise Agilisys have come back with force, billing the grand sum of £460,228.20 for the month, Interestingly, only one invoice for £990 is allocated to the One Barnet programme. Perhaps that is how certain councillors can get away with saying One Barnet hasn't cost that much but it fools no one.
In the financial year 2012-13 Barnet Council have paid Agilisys £3,513,760.99 - yes £3.5 million in one year to one firm of consultants and it brings the total paid to Agilisys to £6,324,366.68 since the start of the One Barnet implementation contract.
Back in July 2012 I raised the issue of Agilisys costs with Barnet’s external auditors, Grant Thornton. This included:
That councillors had been led to believe this contract was going to cost around £2 million and that it looked like on present spending it was going to cost £6 million. As such, were officers legally allowed to exceed this budget by so much without getting further approval for the spending by Councillors and did this make that spending ultra vires.
“I have discussed your second point around the governance of the level of spend on the contract and the Council agrees that it would be good practice to take an update report to the Cabinet Resources Committee. The Council is drafting this report which will update members on the level of spend to date, revised projections for level of spend over the three year period of the contract, value for money considerations (including an update on improved terms negotiated by the Council this year) and plans for the procurement of further support when the current contract ends next year. The report is planned to go to Cabinet Resources Committee at the end of September.”
In the financial year 2012-13 Barnet Council have paid Agilisys £3,513,760.99 - yes £3.5 million in one year to one firm of consultants and it brings the total paid to Agilisys to £6,324,366.68 since the start of the One Barnet implementation contract.
Back in July 2012 I raised the issue of Agilisys costs with Barnet’s external auditors, Grant Thornton. This included:
That councillors had been led to believe this contract was going to cost around £2 million and that it looked like on present spending it was going to cost £6 million. As such, were officers legally allowed to exceed this budget by so much without getting further approval for the spending by Councillors and did this make that spending ultra vires.
On the first point the auditor said,
“With regard to your point on the level of spend, it is
clear that the £2 million figure is an
indicative one. The Council's
2010/11 budget estimates costs of setting up the programme and projects at £3 million.
The spend to date on the contract is approaching £4 million. Although ongoing
spend and value for money is monitored by the Council's Corporate Directors'
Group, there is nothing in the Council's constitution that requires the
reporting back to members for this contract on the basis that there is no maximum contract value set.
From the review of working papers, I am satisfied that there is no need for me
to take formal legal advice as to the legality of the £4 million contract as I
have not seen evidence that the council has acted outside of its powers. Based on these
findings, I have concluded that the Council has followed its own rules in terms
of the nature and level of spend under this contract and that there is no
legality issue that would impact on my ability to certify the 2011/12 audit
closed.”
The Auditor added as a footnote,
“I have discussed your second point around the governance of the level of spend on the contract and the Council agrees that it would be good practice to take an update report to the Cabinet Resources Committee. The Council is drafting this report which will update members on the level of spend to date, revised projections for level of spend over the three year period of the contract, value for money considerations (including an update on improved terms negotiated by the Council this year) and plans for the procurement of further support when the current contract ends next year. The report is planned to go to Cabinet Resources Committee at the end of September.”
Well Mr Hughes, was that September 2012 or September 2013 because as far as I can see no report on this matter has as yet been sent to the Cabinet Resources Committee. 12 months on and we have gone way past the £6 million mark yet not one councillor has formally raised the issue of such a massive overspend.
Personally I think that this is nothing short of a scandal. How a £2 million contract can hit £6.3 million and no one, other than members of the public, asks any questions, is beyond me.
Friday, 5 April 2013
Audit Committee Papers Reveal Shortcomings of One Barnet Outsourcing Advisors
Barnet's Audit Committee will be considering Internal Audit work on Monday. In the Exception Report Internal Audit give a "Limited" Assurance rating on the client side of outsourced legal services (page 18). The three Priority One findings they identified are as follows:
Contract Management - The review identified areas where the client side management of the Joint Legal Service (JLS) contract could be strengthened. There is currently no Contract Manager in place. The Contract Manager post for the JLS will form part of the Commercial arrangements, as part of the retained organisation. However this recruitment process has been delayed since September 2012.
Risk Management -The review found areas where the client side risk management controls could be improved. The Inter Authority Agreement clearly sets out the risk management procedure which the JLS should maintain in the delivery of the service. However, the absence of a Contract Manager may result in this process not operating effectively in practice. Risks noted within the project prior to go ‘live’ were not transferred internally for those retained risks identified.
Benefits Realisation - The review found that there was no documented process in place for ensuring that the cost, quality and effectiveness benefits, set out in the original business case, were regularly monitored and managed to ensure that they are fully realised. The review was unable to identify a nominated person responsible, in the absence of a Contract Manager, for the ongoing monitoring, management and realisation of benefits. The review also found that there were no documented baseline figures for the benefits to be monitored against.
Personally, I find it unacceptable that a service which was outsourced last September still has such fundamental client side short comings. Where were the advisors and why didn't they flag this up as an issue? Getting the client side functions in place is critical to the successful management of any outsourced service. The fact that Barnet cannot measure whether benefits are being realised appears to undermine the entire rationale for outsourcing. If these mistakes are repeated with the NSCSO and DRS contracts it could be an absolute disaster. But hang on a minute....
It is also interesting to note that while not an "Assurance Reports" and therefore no receiving an "assurance" rating there were two management reviews undertaken; one into the KPI's of the NSCSO contract and one for the DRS KPI's.We do not see copies of these reports however, the following summary is included on page 24 of the exception report:
Given that the only reason these contracts haven't been signed yet is because of the Judicial Review, perhaps Barnet should be thanking Maria Nash for helping them to avoid yet another cock up. However, I am also left wondering how such fundamental shortcomings can arise on such a heavily resourced project that has paid millions to consultants an lawyers to avoid exactly these sorts of problems. Frankly I think this demands a an immediate independent review as it may expose many more shortcomings in these two massive outsourcing projects. Richard Cornelius may brand people like me "whingers" but when you read reports like this it is hardly surprising people are concerned.
Contract Management - The review identified areas where the client side management of the Joint Legal Service (JLS) contract could be strengthened. There is currently no Contract Manager in place. The Contract Manager post for the JLS will form part of the Commercial arrangements, as part of the retained organisation. However this recruitment process has been delayed since September 2012.
Risk Management -The review found areas where the client side risk management controls could be improved. The Inter Authority Agreement clearly sets out the risk management procedure which the JLS should maintain in the delivery of the service. However, the absence of a Contract Manager may result in this process not operating effectively in practice. Risks noted within the project prior to go ‘live’ were not transferred internally for those retained risks identified.
Benefits Realisation - The review found that there was no documented process in place for ensuring that the cost, quality and effectiveness benefits, set out in the original business case, were regularly monitored and managed to ensure that they are fully realised. The review was unable to identify a nominated person responsible, in the absence of a Contract Manager, for the ongoing monitoring, management and realisation of benefits. The review also found that there were no documented baseline figures for the benefits to be monitored against.
Personally, I find it unacceptable that a service which was outsourced last September still has such fundamental client side short comings. Where were the advisors and why didn't they flag this up as an issue? Getting the client side functions in place is critical to the successful management of any outsourced service. The fact that Barnet cannot measure whether benefits are being realised appears to undermine the entire rationale for outsourcing. If these mistakes are repeated with the NSCSO and DRS contracts it could be an absolute disaster. But hang on a minute....
It is also interesting to note that while not an "Assurance Reports" and therefore no receiving an "assurance" rating there were two management reviews undertaken; one into the KPI's of the NSCSO contract and one for the DRS KPI's.We do not see copies of these reports however, the following summary is included on page 24 of the exception report:
NSCSO and DRS key performance indicators – a
number of key performance indicators included to measure the success of both
contracts were not robust in terms of data quality. For example, policies and
procedures governing the collection of data were not in existence, some targets
did not have baseline data, some data was inaccurate, and some of the source
data was not adequately
protected from data
loss or data error. These reviews were a proactive audit requested from the
projects to ensure that any issues could be rectified pre-contract sign. Given that the only reason these contracts haven't been signed yet is because of the Judicial Review, perhaps Barnet should be thanking Maria Nash for helping them to avoid yet another cock up. However, I am also left wondering how such fundamental shortcomings can arise on such a heavily resourced project that has paid millions to consultants an lawyers to avoid exactly these sorts of problems. Frankly I think this demands a an immediate independent review as it may expose many more shortcomings in these two massive outsourcing projects. Richard Cornelius may brand people like me "whingers" but when you read reports like this it is hardly surprising people are concerned.