For years I have been raising concerns about Barnet Council spending on agency staff. From a peak of just under £20 million a year in 2016/17 it has been declining and at the current rate should hit around £14.5 million by the year end.
However, I also review the monthly agency spend by department and what I have seen it a rising trend for agency spend in the Streetscene department which includes the refuse collection department. I have yet to see any evidence that the massive round reorganisation that took place in November 2018 has generated a single penny of savings and at the same time I have seen the agency spend continue to rise. Back in June I raised concerns that Streetscene was spending on average £50,000 a week on agency staff but in October that had risen much further and in November we saw two weeks where the agency spend was over £80,000 per week. So what this suggests is that while spend in some departments is falling, any savings are being offset by increases in the Streetscene department and I suspect this is to bolster the disastrous refuse collection changes. The agency spend did decline at the end of the month but that is a reflection of the fact that the green bin collections were paused early (10 November) because of the subsidence problems at the new Oakleigh Road waste depot. Public scrutiny has been gagged in Barnet and as such these trends are simply ignore at committee meetings and I get the impression that most councillors never actually drill down onto the figures.
Capita spend was comparatively low in November because there were no quarterly payments made this month but the running total for the contract to date is still £166.5 million more than was contracted.
2020 should see the 6/7 year review of the two Capita contracts but I have no confidence that they will examine what has been going on and whether Barnet residents are actually getting a good value service. I will keep watching how Barnet are spending our money.
Showing posts with label Bingate. Show all posts
Showing posts with label Bingate. Show all posts
Friday, 3 January 2020
Sunday, 15 September 2019
The Politics of Bins, Rubbish and a Collapsing Depot
Last week the Environment Committee held a very full meeting under the new gagging rules. No public speakers and severe restrictions on questions. Barnet Tories have achieved what they want - no public scrutiny. The agenda was stuffed to the gunwales, two public questions on one item limited to 100 words, no opportunity to speak, same answer to both questions, yet there were so many other issues.
If you live in High Barnet you may be unhappy to learn that Barnet have agreed to give 100 resident parking permits to Barnet General Hospital for their staff to park in residents bays as the hospital's staff car park is full. Interestingly, the no public speaking rule was waived to allow someone from Royal Free Trust to speak about their plans and justify why this should go ahead. Apparently there are plans at some stage to build a multi storey car park but they need this proposal to meet an immediate need. Labour councillors had asked for a review of the CPZ to be undertaken before these new permits were introduced to get local residents views but the Tories were keen to push it through and undertake the review once the hospital had been given the 100 permits. It also touches on a broader issue which is that many of the staff at Barnet General simply can't afford to live in Barnet and hence have to drive in from lower cost areas. This is a problem that is only going to get worse and highlights the failing in the Council's affordable housing strategy (what strategy?)
Onto another serious matter, the review of the Reduction and Recycling Plan (RRP). This is a plan Barnet were required to produce in conjunction with the GLA because of Barnet's withdrawal of the food collection service last year. It has taken a long time to get this report, and I have to say I found it very interesting. It highlights that Barnet is slipping down the rankings in recycling rates from 11th to 15th of the London boroughs with most of the lower ranking boroughs being the inner London ones.
What the independent consultants report identified was a series of options ranging from the status quo plus food waste collection to fortnightly collections of general and recycled waste.
The options also looked at the introduction of charging for green waste collection at a cost of £35 or £50 per annum, something that was mooted last year and has yet to be confirmed.
What the study did reveal was that simply adding back in a weekly food waste collection service would cost an extra £1.26 million a year. I found this somewhat surprising as the justification for its removal was a saving of just £300,000 a year. So scrapping a service which will now have to reintroduce by 2022 at the latest has cost us at least an extra million quid. This is because they have bought 16 new refuse vehicles, 4 in October and another 12 last month at a total cost of £3.2 million. However, these new vehicles cannot collect the food waste separately on the same vehicle (which is how they previously operated the service) so they will have to buy and operate a new fleet of dedicated food waste collection lorries.
What the report also shows is that the option of weekly food and recycling collections with fortnightly general waste collections (Option 3) could save over £400,000 a year and boost recycling rates from the current level of 34.6% to a respectable 48.2%. While this seems like the most sensible option, in Barnet sensible doesn't cut it. The Tory party manifesto focused on keeping weekly bin collections in spite of the fact that three quarters of English Local authorities have already moved to fortnightly (or even less frequent) collections.
This report does include the treatment costs of waste and it confirms what I said last year that anaerobic digestion of food waste will continue to be significantly cheaper than burning it with the general refuse. Interestingly, last week Barnet also published a report on the cost and savings generated by the refuse rounds reorganisation when the food waste collection ceased. That shows a net saving of just £335,000 but ignores the additional cost of waste disposal. Add that back in and the savings fall to just £50,000. That looks like an incredibly bad decision now that we know we will have to reintroduce food waste collections at a cost of £1.26 million.
When pressed as to whether Barnet will ever reinstate the food waste collection they repeated said that it was their "aim" but would be influenced by the cost of the service. Anyone listening to what was being said will be in no doubt that the food waste collection service will not be reintroduced while we have a Tory council in charge.
What caps all of these problems off is the continuing subsidence at the new Oakleigh Road depot. This is a scheme that was rushed into at great expense even though it was inadequate for our needs resulting in Barnet having to rent additional depot space from Harrow Council. Capita project managed the depot delivery at this site even though it was known for problems with subsidence. Within weeks of the depot opening cracks began to appear and the problem has simply got worse. Some cosmetic repairs were done filling in the cracks but the problem has never gone away. At last week's meeting it was announced that the problems had become much worse over the summer and that major works were now necessary as a matter of urgency. This will need to start in November, taking six month to complete and is likely to cause significant disruption including weekend working, reduced number of vehicles at the depot and use other satellite depots. There are likely to be additional costs over and above the remedial works, such as the extra costs of renting space, paying staff to work weekends etc. but it is not clear who will be picking up the tab for these costs and as the officer said they will be "part of a commercial discussion" as to who pays. Willmott Dixon are the builders but I cannot understand why Capita who were responsible for project managing this scheme and have been paid a large sum on top of their core contract fee, allowed this to happen and to drag on for such a long time that such serious and disruptive works are now necessary.
As ever, we will never get to the bottom of this saga as Barnet hate any form of criticism of them or their contractors.
If you live in High Barnet you may be unhappy to learn that Barnet have agreed to give 100 resident parking permits to Barnet General Hospital for their staff to park in residents bays as the hospital's staff car park is full. Interestingly, the no public speaking rule was waived to allow someone from Royal Free Trust to speak about their plans and justify why this should go ahead. Apparently there are plans at some stage to build a multi storey car park but they need this proposal to meet an immediate need. Labour councillors had asked for a review of the CPZ to be undertaken before these new permits were introduced to get local residents views but the Tories were keen to push it through and undertake the review once the hospital had been given the 100 permits. It also touches on a broader issue which is that many of the staff at Barnet General simply can't afford to live in Barnet and hence have to drive in from lower cost areas. This is a problem that is only going to get worse and highlights the failing in the Council's affordable housing strategy (what strategy?)
Onto another serious matter, the review of the Reduction and Recycling Plan (RRP). This is a plan Barnet were required to produce in conjunction with the GLA because of Barnet's withdrawal of the food collection service last year. It has taken a long time to get this report, and I have to say I found it very interesting. It highlights that Barnet is slipping down the rankings in recycling rates from 11th to 15th of the London boroughs with most of the lower ranking boroughs being the inner London ones.
What the independent consultants report identified was a series of options ranging from the status quo plus food waste collection to fortnightly collections of general and recycled waste.
The options also looked at the introduction of charging for green waste collection at a cost of £35 or £50 per annum, something that was mooted last year and has yet to be confirmed.
What the study did reveal was that simply adding back in a weekly food waste collection service would cost an extra £1.26 million a year. I found this somewhat surprising as the justification for its removal was a saving of just £300,000 a year. So scrapping a service which will now have to reintroduce by 2022 at the latest has cost us at least an extra million quid. This is because they have bought 16 new refuse vehicles, 4 in October and another 12 last month at a total cost of £3.2 million. However, these new vehicles cannot collect the food waste separately on the same vehicle (which is how they previously operated the service) so they will have to buy and operate a new fleet of dedicated food waste collection lorries.
What the report also shows is that the option of weekly food and recycling collections with fortnightly general waste collections (Option 3) could save over £400,000 a year and boost recycling rates from the current level of 34.6% to a respectable 48.2%. While this seems like the most sensible option, in Barnet sensible doesn't cut it. The Tory party manifesto focused on keeping weekly bin collections in spite of the fact that three quarters of English Local authorities have already moved to fortnightly (or even less frequent) collections.
This report does include the treatment costs of waste and it confirms what I said last year that anaerobic digestion of food waste will continue to be significantly cheaper than burning it with the general refuse. Interestingly, last week Barnet also published a report on the cost and savings generated by the refuse rounds reorganisation when the food waste collection ceased. That shows a net saving of just £335,000 but ignores the additional cost of waste disposal. Add that back in and the savings fall to just £50,000. That looks like an incredibly bad decision now that we know we will have to reintroduce food waste collections at a cost of £1.26 million.
When pressed as to whether Barnet will ever reinstate the food waste collection they repeated said that it was their "aim" but would be influenced by the cost of the service. Anyone listening to what was being said will be in no doubt that the food waste collection service will not be reintroduced while we have a Tory council in charge.
What caps all of these problems off is the continuing subsidence at the new Oakleigh Road depot. This is a scheme that was rushed into at great expense even though it was inadequate for our needs resulting in Barnet having to rent additional depot space from Harrow Council. Capita project managed the depot delivery at this site even though it was known for problems with subsidence. Within weeks of the depot opening cracks began to appear and the problem has simply got worse. Some cosmetic repairs were done filling in the cracks but the problem has never gone away. At last week's meeting it was announced that the problems had become much worse over the summer and that major works were now necessary as a matter of urgency. This will need to start in November, taking six month to complete and is likely to cause significant disruption including weekend working, reduced number of vehicles at the depot and use other satellite depots. There are likely to be additional costs over and above the remedial works, such as the extra costs of renting space, paying staff to work weekends etc. but it is not clear who will be picking up the tab for these costs and as the officer said they will be "part of a commercial discussion" as to who pays. Willmott Dixon are the builders but I cannot understand why Capita who were responsible for project managing this scheme and have been paid a large sum on top of their core contract fee, allowed this to happen and to drag on for such a long time that such serious and disruptive works are now necessary.
As ever, we will never get to the bottom of this saga as Barnet hate any form of criticism of them or their contractors.
Labels:
Barnet Council,
Bingate,
Capita,
depot subsidence,
no savings,
Oakleigh Rd depot,
Rubbish
Thursday, 4 April 2019
Disappearing Evidence - Refuse Collection Reorganisation Update
Update 11.29 am 5 April.
I have just had a response from Barnet that the information is now available again. You can see it here. Having checked the data, the overspend on waste collection service remains the same at £2.029 million.
On 14 March I asked a series of questions relating to the round reorganisation of Barnet's waste collection service. I expressed serious concern that not only had the rounds reorganisation not saved any money but in fact it had actually cost a great deal more. The reason for me making this assertion was based on information issued at the Financial Performance & Contracts Committee a few days earlier on 11 March. At that meeting it was disclosed that the waste collection service was significantly over budget and that the year end forecast showed the service would be £1.75 million over spent and that this overspend had jumped £1.189 million since the previous month. I raised this at the Environment Meeting but received no clear response as to when we would get a clear understanding of what the reorganisation has actually cost.
On 1 April Barnet published the Period 11 financial figures which also set out how the latest forecast on the waste collection service had worsened. Luckily I took a snapshot of this report. On the 2 April I tweeted about the significant increase in costs but as of 12 noon today the information has been removed from the website - it looks like it was removed on 2 April, possibly as a result of my tweet.
The figures show that between the figures published on 11 March and those published on 1 April the revised year end forecast had increased by another £283,000. That is a huge increase in short a short period of time. Much worse is that they were forecasting for the last three months of the year in the period 9 figures. To have to make such a large adjustment in period 11 suggests that cost have rocketed at a time when I was told repeatedly at the Environment Committee that the problems with waste collection were reducing. It is now apparent that the reason the problem are reducing is because so much more money is being thrown at them. I have set out below a comparison between the two sets of figures including the one that has now been removed from the Council's (not very) Open Data website.
I have asked Barnet why they have removed these figures and I will update this post once I have a response. What is clear to me is that the round reorganisation of the waste service has been a financial disaster and the risk is that other cuts to services will now be made to offset this massive overspend.
I have just had a response from Barnet that the information is now available again. You can see it here. Having checked the data, the overspend on waste collection service remains the same at £2.029 million.
On 14 March I asked a series of questions relating to the round reorganisation of Barnet's waste collection service. I expressed serious concern that not only had the rounds reorganisation not saved any money but in fact it had actually cost a great deal more. The reason for me making this assertion was based on information issued at the Financial Performance & Contracts Committee a few days earlier on 11 March. At that meeting it was disclosed that the waste collection service was significantly over budget and that the year end forecast showed the service would be £1.75 million over spent and that this overspend had jumped £1.189 million since the previous month. I raised this at the Environment Meeting but received no clear response as to when we would get a clear understanding of what the reorganisation has actually cost.
On 1 April Barnet published the Period 11 financial figures which also set out how the latest forecast on the waste collection service had worsened. Luckily I took a snapshot of this report. On the 2 April I tweeted about the significant increase in costs but as of 12 noon today the information has been removed from the website - it looks like it was removed on 2 April, possibly as a result of my tweet.
The problem is that street scene are massively over budget because of the botched #bingate fiasco. The latest figures show that waste is £2m over budget, up £283k since 11 March figures. I suspect managers are franticly making cuts to balance budgets without consulting Cllrs. pic.twitter.com/YBaQKT9fws— Mr Reasonable (@ReasonableNB) April 2, 2019
The figures show that between the figures published on 11 March and those published on 1 April the revised year end forecast had increased by another £283,000. That is a huge increase in short a short period of time. Much worse is that they were forecasting for the last three months of the year in the period 9 figures. To have to make such a large adjustment in period 11 suggests that cost have rocketed at a time when I was told repeatedly at the Environment Committee that the problems with waste collection were reducing. It is now apparent that the reason the problem are reducing is because so much more money is being thrown at them. I have set out below a comparison between the two sets of figures including the one that has now been removed from the Council's (not very) Open Data website.
I have asked Barnet why they have removed these figures and I will update this post once I have a response. What is clear to me is that the round reorganisation of the waste service has been a financial disaster and the risk is that other cuts to services will now be made to offset this massive overspend.
Labels:
Barnet Council,
Bingate,
massive overspend
Tuesday, 12 March 2019
Barnet Bingate - My questions on what happened

Questions:
Preparation Stage:
- Why wasn’t a survey of the number of bins collected from households carried out before the rounds were finalised and has it now been completed?
- The report acknowledges there was over confidence in drivers abilities to access challenging roads. Was a representative of the drivers invited to test drive the new larger vehicles before they were purchased?
- Was the purchase of wider longer vehicles included in the risk assessment and if so, what was the finding and how was the risk mitigated?
- I understand from industry experts from outside Barnet that one of the downsides of route planning software is that it does not always pick up road anomalies and as such should always be validated by staff with a detailed route knowledge to “sense check” them. How many of the routes were “sense checked” by experienced staff before they were introduced and how many were amended following that sense checking?
- Does the route planning software easily accommodate manual amendments to the proposed routes?
- Given that some roads may have 6 or more sections, as highlighted at 4.3 in the report, on how many occasions does the route planning software schedule two or more different refuse vehicles, two or more recycling vehicles and two or more green waste vehicles in the same road on the same day, what is the maximum number of different vehicles that have been scheduled for collections in the same road in a single day?
- Can you confirm that the area based collection strategy means that, for example, on a Monday, refuse vehicles based in Harrow would have to travel to the East of the borough before they start work and return to Harrow at the end of their shift and that on a Friday, for example, vehicles based at Oakleigh Road would have to travel to the West of the borough before they start collecting and return to Oakleigh Road at the end of their shift and how much of their shift is spent travelling from one side of the borough not collecting rubbish?
- Did anyone calculate the mileage, travel time and fuel costs associated with the area based collection strategy and if so what is the additional mileage, travel time and fuel cost compared to the old collections rounds?
- Can you clarify if, prior to the route change, drivers only had to have a knowledge of roads in the half of the borough where they were based whereas now they have to have a knowledge of roads all across the borough?
- Can you clarify if any members of the frontline staff, such as drivers, were members of the project team?
- The report notes that from 27 August frontline staff were invited to take part in structured review sessions. How many staff were invited, how many sessions were held and how many frontline staff attended?
- On page 36 the report states that Street Scene is in the process of procuring a fully integrated IT system. What is the cost of this and why wasn’t it procured before the round changes were made?
- The calculation of total staff numbers in figure 13 do not add up. Please can you clarify what are the correct figures?
- It appears that the number of core staff have reduced by approximately 15 since October (core LBB staffing has reduced by approximately 600 hours per week). Was the reduction due to increased sickness, staff made redundant or did they leave and if they did leave what did their exit interviews identify as the reason for leaving?
- Of the 7,117 of agency staff hours worked in January, what was the split between drivers and loaders?
- The cost of LBB staff per hour appears to peak in January. Is that linked to bonus payments to incentivise staff to work over the Christmas/New Year period and how much was paid in incentive bonuses to LBB staff?
- In October, before the changes, LBB staff additional hours were approximately 17% of core hours but by December that had risen to approximately 27% of core hours. What impact did such a high level of overtime in November and December have on staff and did it result in the increased level of sickness/unauthorised absence?
- What check were made at the time to ensure drivers did not exceed maximum driving hours and has a review taken place of all tachograph charts/written records to audit those checks?
- How many hours of other street scene staff were diverted from, for example, street cleaning duties, to refuse collection and has this had a detrimental effect on the standard of street cleanliness?
- Is the plan to keep the high proportion of agency staff or is it the intension to recruit permanent staff to phase out the majority of agency staff?
- Given that in the UK over the last 5 years 39 waste workers have been killed mostly by being hit by moving vehicles or machinery, and that as recently as December a refuse worker in Northholt was killed, what safety training is provided to agency staff and permanent staff and has a risk assessment been carried out on the model of using such a high proportion of agency staff?
- How many rounds were in operation before the changes and how many rounds are there now split between general waste, recycling and garden waste?
- What is the average number of collections for each of the garden waste rounds?
- How many of the new rounds are completed within a standard 8 hour shift and how many rounds need additional overtime or agency staff assistance to complete?
- Can you clarify if situations arise where the vehicle driver is based in one depot but the loaders for that vehicle are based in the other depot?
- Can you clarify who is now collecting waste from residential properties above shops, household waste teams or trade waste teams, and what have been the operational implications of the changes?
- Of the 10 additional refuse vehicles on hire each week how many are to replace broken down vehicles and how many are to provide additional capacity on rounds?
- In addition to the vehicles on hire, how many refuse vehicles have been purchased and what was the cost?
- How often are general waste vehicles left full overnight and what impact does that have on start time of rounds the next morning?
- Is green waste held at the Oakleigh Road depot overnight and how often is it sent to Edmonton?
- How often is recycling waste held in the bulking areas at the Oakleigh Road Depot overnight, and is this a fire risk?
- How many LBB shunt vehicles are used to transfer waste from Oakleigh Road to Edmonton and has this been reduced/outsourced since the new round changes?
- In January you were operating an afternoon crew working between 2pm – 9pm at the Oakleigh Road Depot. Is that shift still operating and is it a permanent component of the collection service?
- How many accident/damages claims have been made since the new larger vehicles were introduced and how does that compared to the number of claims made before the new vehicles were introduced?
- On how many estates have you cut the number of collections from twice weekly to once a week and how much has that saved?
- If you are now rebalancing Monday and potentially Tuesday and collection rounds are moved to new days, how will this affect area based working?
- The report identifies that there were only 225 formal complaints in the three months November, December and January yet during that time there were over 16,000 reported missed bin collections. Many residents reported that they simply couldn’t get through the switchboard. Why did the publicity material not contain a designated hotline number and why was the customer service response so poor?
- Has the on-going problem with subsidence at the Oakleigh Road Depot impacted on the efficiency of the operation such as restricting vehicle movements or parking within the depot and when will the subsistence problems be resolved?
- Given that space at the Oakleigh Rd depot is very restricted, how have the additional purchased and hired vehicles been managed in terms of parking, does it reduce the efficiency of the depot and was an appropriate risk assessment completed to ensure the movement of so many vehicles in such a tight space was carried out safely?
- Please provide a clear summary of the weekly cost of general, recycling and garden waste collections before the changes and the costs after the changes including the additional vehicle hire, additional fuel costs so that we can understand how much the new changes have saved/cost?
- Period 10 to end of year forecast for the Waste and Recycling Front Line budget indicates it will be £1.75 million overspent. Given that any changes of this scale are recognised within the waste management industry as taking between three and six months for full business as usual, why wasn’t this period of disruption and associated costs not built into the budget?